Improvements Underway at Olive Branch

By David Taylor, Jr., Aviation Director
Olive Branch Airport

The Olive Branch Airport is in the midst of several improvement projects for 2025. Phase I of the taxiway refurbishment is underway and is expected to be completed the second week of June. Along with that is the south ramp partial refurbishment project ahead of a new 12,000 square-foot corporate hangar build, also to begin in the second week of June. Future projects include the addition of an avgas storage tank, Phase II south ramp refurbishment, Phase II & III taxiway refurbishment and control tower improvements.